For an activity with more than one immediate successor activity, its latest finish time is equal to the Group of answer choices largest latest finish time among its immediate successors. smallest latest finish time among its immediate successors. largest latest start time among its immediate successors. smallest latest start time among its immediate successors.

+4
Answers (1)
  1. 1 January, 10:40
    0
    Smallest latest start time among its immediate successors.

    Explanation:

    All activity, (with the exception of the end activity) is expected to have at least one successor. The end activity has zero successors. It is only essential to state the immediate predecessors for the activities to describe the project. An immediate predecessor is the predecessor that is not referred by two or more predecessor relationships.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “For an activity with more than one immediate successor activity, its latest finish time is equal to the Group of answer choices largest ...” in 📙 Computers & Technology if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers