Ask Question
23 March, 07:47

In which contingency plan testing strategy do individuals follow each and every IR/DR/BC procedure, including the interruption of service, restoration of data from backups, and notification of appropriate individuals?

a. Full-interruption

b. Desk check

c. Simulation

d. Structured walk-through

+5
Answers (1)
  1. 23 March, 11:15
    0
    Answer:Full-interruption--A

    Explanation: The Full-interruption is one of the major steps for a Disaster Recovery Plan, DRP which ensures businesses are not disrupted by saving valuable resources during a disaster like a data breach from fire or flood.

    Although expensive and very risky especially in its simulation of a disruption, this thorough plan ensures that when a disaster occurs, the operations are shut down at the primary site and are transferred to the recovery site allowing Individuals follow every procedure, ranging from the interruption of service to the restoration of data from backups, also with the notification of appropriate individuals.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “In which contingency plan testing strategy do individuals follow each and every IR/DR/BC procedure, including the interruption of service, ...” in 📙 Computers & Technology if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers