How long does it take 2 consultants to create a slide deck of 120 slides, assuming one consultant make 2 slides per hour?

+5
Answers (1)
  1. 30 July, 00:23
    0
    It would take 2 consultants 30 hours to create a slide deck of 120 slides.

    Explanation:

    Rate of slide making by one consultant - 2 slides per hour

    Target - 120 slides

    2 consultants are employed in the job-

    Since 2 consultants are employed in the job, total rate of making slides per hour would be 4 slides/hour (2*2 slides/hour)

    Time required to complete 120 slides = total slides/rate of doing slides per hour

    Substituting the values, we get

    Time required = 120/4 = 30 hours

    Hence, it would take 30 hours for 2 consultants to create a slide deck of 120 slides.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “How long does it take 2 consultants to create a slide deck of 120 slides, assuming one consultant make 2 slides per hour? ...” in 📙 Computers & Technology if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.