Which logical relationship does the PDM usemost often?

Start to finish

Start to start

Finish to finish

Finish to start

+1
Answers (1)
  1. 9 March, 15:29
    0
    Finish to Start.

    Explanation:

    Finish to Start dependency also known as FS is most commonly used dependency type used between activities in PDM (Precedence Diagramming Method). For example : - in a software you cannot test a screen before it is developed, in construction you cannot paint a building before it is constructed. So we conclude that Finish to start is most commonly used.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Which logical relationship does the PDM usemost often? Start to finish Start to start Finish to finish Finish to start ...” in 📙 Computers & Technology if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.