Ask Question
2 April, 00:28

With 10,000 per day who would be the apparent low bidder; Bidder A was $500,000 and estimated completion date of 200 days. Bidder B was $540,000 and a completion day and estimated completion date of 180.

1. Bidder B

2. Bidder A

+5
Answers (1)
  1. 2 April, 00:47
    0
    Bidder B is the lower bidder. the option (A) is correct

    Explanation:

    Solution

    Given that:

    Bidder A = $500,000

    The estimate completion time = 200 days

    Bidder B = $540,000

    The estimate completion time = 180 days

    Overhead charges = $10,000/day

    Now,

    The Total Bid of A (including overhead charges) = 500,000 + 200 * 10000

    = 500,000 + 2000000

    =$2,500,000

    The Total Bid for B (Including overhead charges) = 540,000 + 180 * 10000

    =540,000 + 1,800,000

    =$2340000

    Hence Bidder B is apparently a low bidder, since the Total Bid of B is lower than the Total Bid of A.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “With 10,000 per day who would be the apparent low bidder; Bidder A was $500,000 and estimated completion date of 200 days. Bidder B was ...” in 📙 Engineering if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers