Ask Question
11 June, 13:50

N operation has a 10 percent scrap rate. as a result, 72 pieces per hour are produced. what is the potential increase in labor productivity that could be achieved by eliminating the scrap

+5
Answers (1)
  1. 11 June, 17:10
    0
    100% - 10% = 90%

    90% = 0.90

    72/0.90 = 80

    they should produce 80 parts per hour which is an 8 part increase
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “N operation has a 10 percent scrap rate. as a result, 72 pieces per hour are produced. what is the potential increase in labor productivity ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.