A firm produces 500 units per week. it hires 20 full-time workers (40 hours/week) at an hourly wage of $15. raw materials are ordered weekly and they costs $10 for every unit produced. the weekly cost of the rent payment for the factory is $2,250. how do the overall costs breakdown

+5
Answers (2)
  1. 25 March, 10:40
    0
    Raw material for 500 units per week = 500 x $10 = $5000

    Cost of hiring 20 workers per week = 20 x 40 x 25 = $12000

    Rental = $2250

    Total = 5000 + 12000 + 2250 = $19 250
  2. 25 March, 11:38
    0
    The total answer is = $ 19 250
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A firm produces 500 units per week. it hires 20 full-time workers (40 hours/week) at an hourly wage of $15. raw materials are ordered ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.