An electrician was hired to wire a new house. In 11 1/4 days he estimates he has completed 70% of the job. At his current pace of work, how long will it take him to complete the entire job?

+2
Answers (1)
  1. 31 March, 18:10
    0
    It will take him about 16.07 days.

    To solve this problem, you can write a proportion to find the amount of time.

    11.25 days / 70% = x days / 100%

    If you cross multiply and divide this, you will get about 16.07.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “An electrician was hired to wire a new house. In 11 1/4 days he estimates he has completed 70% of the job. At his current pace of work, how ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.