If A completes a particular work in 8 days and B the same work in 24 days. How many days will it take if they work together?

+2
Answers (1)
  1. 2 January, 05:36
    0
    A:

    1 day = 1/8 of work

    B:

    1 day = 1/24 of the work

    Together:

    1 day = A + B = 1/8 + 1/24 = 4/24 = 1/6

    1 day = 1/6 of work

    1/6 x 6 of work = 1 x 6 days

    work = 6 days