The first unit of production takes 20 hours to produce and the learning rate is expected to be 90 percent. how long will it take to produce the twelfth unit? less than or equal to 11.0 hours greater than 11.0 hours but less than or equal to 13.0 hours greater than 13.0 but less than or equal to 15.0 hours greater than 15.0 hours

+2
Answers (1)
  1. 3 December, 15:31
    0
    Learning curve rate, r, means the ratio of production time satisfies the relation

    T_2k=r*T_k

    solving the equation gives

    T (n) = (T_initial) * (n^b) where b=log (r) / log (2)

    Here, r=0.9 = > b=log (0.9) / log (2) = - 0.15200

    n=12, T_initial=20

    =>

    T (12) = 20*12^ (-0.15200) = 13.71 hours
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The first unit of production takes 20 hours to produce and the learning rate is expected to be 90 percent. how long will it take to produce ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers