30men can finish 1/7of a work in 2days. 18men will do othe remaining work in?

+1
Answers (1)
  1. 17 March, 01:58
    0
    7/7-1/7=6/7 is the rest of work

    1/7 work takes 2days

    6*1/7=6/7 work takes 6*2days=12days

    30 men takes 12 days to finish the rest of work (6/7)

    18 men takes 18*12/30 = 7.2days