If workers were able to pave 1/3 of your driveway in 40 minutes if they work at same rate what portion of driveway will they pave in one hour

+1
Answers (1)
  1. 21 September, 11:49
    0
    40min is 1/3

    implies 20min is 1/6

    60min is 1/3+1/6=3/6=1/2
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “If workers were able to pave 1/3 of your driveway in 40 minutes if they work at same rate what portion of driveway will they pave in one ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.