Sam constructs 3/4 of the wall in 1 2/3 days. How many days will he need to construct the wall? Simplify your answer and write it as a proper fraction or as a whole or mixed number. Sow your work.

+3
Answers (2)
  1. 3 April, 12:24
    0
    3/4w=5/3

    => w=5/3*4/3=20/9=2 1/9 days
  2. 3 April, 14:02
    0
    5/3 days for 3/4 of Wall, so

    5/3*4/3 days for 3/4*4/3 = 1 Wall

    Or 20/9 (2_2/9) days.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Sam constructs 3/4 of the wall in 1 2/3 days. How many days will he need to construct the wall? Simplify your answer and write it as a ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.