20 February, 00:36

In an assignment method problem, if it takes abe 3 hours to build a birdhouse and 4 hours for a doghouse, while betty takes 4 hours for a birdhouse and 3 hours for a doghouse, what is the reduced cost (in hours) of assigning abe to build the doghouse? 0 hours 1 hour 2 hours 3 hours 4 hours

+2
Answers (1)
  1. 20 February, 03:28
    0
    4 hours because it shows you that it is like the hours it takes him
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “In an assignment method problem, if it takes abe 3 hours to build a birdhouse and 4 hours for a doghouse, while betty takes 4 hours for a ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.