A 13 1/2 kilometer stretch of road needs repairs. Workers can repair 2 1/4 kilometer of road per week how many weeks will it's take to repair this stretch of road

+1
Answers (1)
  1. 7 April, 21:13
    0
    6 weeks

    Workers can repair 4 1/2 miles of road in two weeks. Double that to get 9 miles in four weeks. Add another 4 1/2 miles in two weeks to get 13 1/2 miles. That's a total of six weeks.

    You can also just multiply 9/4 by 6:

    9/4x6=54/4=13.5, or 13 1/2.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A 13 1/2 kilometer stretch of road needs repairs. Workers can repair 2 1/4 kilometer of road per week how many weeks will it's take to ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.