In three hours, manufacturer z can make b ball bearings. manufacturer y can make b ball bearings in 4 hours. manufacturer x can make b ball bearings in 6 hours. working together, how long will it take all three plants to make b ball bearings?
+5
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “In three hours, manufacturer z can make b ball bearings. manufacturer y can make b ball bearings in 4 hours. manufacturer x can make b ball ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.