5 February, 11:14

A construction company will be fined for each day it is late completing its current project. The daily fine will be $4000 for the first day and will increase by $1000 each day. Based on its budget, the company can only afford $60,000 in total fines. What is the maximum number of days it can be late?

+5
Answers (2)
  1. 5 February, 14:26
    0
    60000

    -4000

    56,000

    -5000

    51,000

    -6000

    45,000

    -7000

    38,000

    -8000

    30000

    -9000

    21,000

    -10,000

    11,000

    -11000

    0

    Total of 8 days
  2. 5 February, 14:40
    0
    The maximum number of days is 8days.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A construction company will be fined for each day it is late completing its current project. The daily fine will be $4000 for the first day ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.