A new sidewalk will be 5 feet wide, 240 feet long and filled to a depth of 6 inches (0.5 foot) with concrete. How many cubic yards of concrete are needed

+3
Answers (1)
  1. 27 March, 14:17
    0
    22.22 cubic yards

    Solution:

    Given dа ta:

    Length of the side walk = 240 feet

    Breadth of the side walk = 5 feet

    Height of the side walk = 6 inches = 0.5 feet

    Volume = length * breadth * height

    = 240 * 5 * 0.5

    = 600 cubic feet

    Volume = 600 cubic feet

    Let us convert cubic feet to cubic yard.

    27 cubic foot = 1 cubic yard

    600 cubic feet = 600 : 27

    = 22.22 cubic yard

    Hence 22.22 cubic yards of concrete are needed.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A new sidewalk will be 5 feet wide, 240 feet long and filled to a depth of 6 inches (0.5 foot) with concrete. How many cubic yards of ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.