The Montenegro Flooring Company can replace 200 square feet of carpet with tile in one day They accept a job replacing carpet with tile in an apartment that measures 977.5 square feet How many days will it take the Montenegro Flooring Company to complete this job?

+1
Answers (1)
  1. 18 March, 09:23
    0
    The answer is: it will tak 4.8 days, round this up to 5 days.

    Step-by-step explanation:

    There are 977.5 square feet total for the job. They can do 200 square feet a day. Divide the total by the daily amount to get how many days:

    977.5 / 200 = 4.8. Round this up to 5 days.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The Montenegro Flooring Company can replace 200 square feet of carpet with tile in one day They accept a job replacing carpet with tile in ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.