Ask Question
17 November, 04:24

True or false: The variable overhead rate variance uses the same basic formula as the labor rate variance except that the variable overhead rates are used instead of the direct labor rates.

+2
Answers (1)
  1. 17 November, 04:38
    0
    True

    Step-by-step explanation:

    The variable overhead rate variance refers to the difference in two variables.

    The Variables are

    1. The actual variable manufacturing overhead

    2. The expected variable overhead given the number of hours worked

    Labor rate variance is evaluated by

    AH (AR - SR)

    AH = actual hours

    AR = actual rate

    SR = standard rate.

    The variable overhead rate variance is also calculated the same way except that it replaces the direct labor rates with variable overhead rates
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “True or false: The variable overhead rate variance uses the same basic formula as the labor rate variance except that the variable overhead ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers