A plumber laying 500meters of drain pipe requires 20men working for 10days. What length in meters would be laid by 50men in 5days, if they all work at same rate?

+3
Answers (1)
  1. 17 March, 19:05
    0
    50men working in 5days will lay 100 meters

    Step-by-step explanation:

    If 20men working for 10days lays 500meters

    then, 1 man will lay 10,000 meters in 10 days

    also, 1 man will lay 1000 meters in 1 day

    If 1 man lays 1000 meters in 1 day,

    Then, 50 men will lay (1000 meters / 50); 20 meters in 1 day

    also, the same 50 men will lay (20 meters x 5days); 100 meters in 5 days.

    Therefore, 50men working in 5days will lay 100 meters
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A plumber laying 500meters of drain pipe requires 20men working for 10days. What length in meters would be laid by 50men in 5days, if they ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.