30 Labour s take 20 days to complete a work. How many labour must be added to complete the same work in 15 days?

+1
Answers (1)
  1. 26 December, 21:58
    0
    30 labours ... 20 days

    x ... 15 days

    x = (30*20) / 15=2*20=40 labours.

    Labours added: 40-30=10

    Answer: 10 labours added.