You work as a librarian for a local community college. A

recent report on publishing project shows that show that

57.75% of the project has been completed in the past 7

work days. If work continues at the same rate,

approximately how many work days will be required in

total for the entire project?

Your answer

+3
Answers (1)
  1. 13 December, 15:49
    0
    13 days

    Step-by-step explanation:

    Requires a lot of math steps:

    Division, multiplication, and 100% effort.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “10 poi You work as a librarian for a local community college. A recent report on publishing project shows that show that 57.75% of the ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.