Task F has duration of 10 days and an earliest start date of 20 days. Based on the given data, determine the finish date for task F.

+3
Answers (1)
  1. 9 November, 06:07
    0
    30 days

    Step-by-step explanation:

    Task F duration = 10 days

    Earliest start date = 20 days

    Finish Date of task F = ?

    Earliest start time is the time schedule for a project to begin.

    Earliest finish time is the earliest time at which the task can be finished.

    Earliest finish time is the sum of the earliest start date and activity time.

    Finish date = Earliest start time + Task duration

    = 20 + 10

    = 30 days

    Hence, the the finish time of the task is 30 days.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Task F has duration of 10 days and an earliest start date of 20 days. Based on the given data, determine the finish date for task F. ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.