gram panchayat decides to construct a road in a village. the contract etimates that 25 people can complete the constructin in 24 days. but 5 more people join. how long will they take to complete the job?
+5
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “gram panchayat decides to construct a road in a village. the contract etimates that 25 people can complete the constructin in 24 days. but ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.