gram panchayat decides to construct a road in a village. the contract etimates that 25 people can complete the constructin in 24 days. but 5 more people join. how long will they take to complete the job?

+5
Answers (1)
  1. 24 January, 16:18
    0
    20 days

    Step-by-step explanation:

    If the number of man-days is constant, the time required is inversely proportional to the number of workers. That means 6/5 as many people should be able to do the work in 5/6 as many days:

    (5/6) (24 days) = 20 days
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “gram panchayat decides to construct a road in a village. the contract etimates that 25 people can complete the constructin in 24 days. but ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.