Calculator To determine how to crash activity times,

a. shortest times with crashing must be known.

b. normal activity costs and costs under maximum crashing must be known.

c. realize that new paths may become critical.

d. All of these choices are correct.

+4
Answers (1)
  1. 22 December, 22:03
    0
    To determine how to crash activity times:

    d. All of these choices are correct.

    Step-by-step explanation:

    To determine and calculate the crash activity times:

    We should know the shortest times with crashing. We should know the normal activity and costs under maximum crashing. We should realize that new paths can become critical.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Calculator To determine how to crash activity times, a. shortest times with crashing must be known. b. normal activity costs and costs ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers