To make concrete it take 8 parts crushed gravel, 7 parts water and 5 parts cement mix. A worker needs to make 220 kg of concrete. How much gravel, water and cement mix is needed.

+1
Answers (1)
  1. 30 June, 23:49
    0
    A complete load of concrete = 8 parts gravel + 7 parts water + 5 parts cement.

    Total number of parts in every load = 8 + 7 + 5 = 20 parts

    If total load = 220 kg, then 20 parts = 220 kg

    Divide each side by 20 : 1 part = 11 kg

    gravel = 8 parts = 8 x 11 kg = 88 kg

    water = 7 parts = 7 x 11 kg = 77 kg

    cement = 5 parts = 5 x 11 kg = 55 kg

    Check: 88 + 77 + 55 = 220 yay!
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “To make concrete it take 8 parts crushed gravel, 7 parts water and 5 parts cement mix. A worker needs to make 220 kg of concrete. How much ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.