A construction worker estimates that a kitchen remodel will take 1 person 120 hours. If 4 people work on the job for 6 hours a day, how many days will it take for them to complete the job?

+4
Answers (1)
  1. 11 March, 23:22
    0
    it would take five days for them to complete their job if you want an explanation just ask
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A construction worker estimates that a kitchen remodel will take 1 person 120 hours. If 4 people work on the job for 6 hours a day, how ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.