it takes 2 days to repair 150 meters of road, at that rate how long will it take to repair 2 kilometers of road

+2
Answers (1)
  1. 21 May, 10:28
    0
    It will take 26.6days to repair

    2 kilometers of road

    Step-by-step explanation:

    Solution

    Given that it takes 2days to repair 150 meters of road

    Using this same rate to calculate how long it takes to repair a 2kilometer road

    Let us express kilometers in meters for simplicity

    In meter we have 2*1000m

    =2000m

    Hence If

    150meters takes 2days

    2000 meters takes Xdays

    By cross multiplication we have

    X days = (2000*2) / 150

    X days = 4000/150

    X = 26.6days