a person hour is a unit of measure representing one person working for one hour. A construction foreman estimates it will take 2880 person-hours to build a new library. If 12 workers are scheduled to work on the project at the same time, how many hours will it take to complete the project
+3
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “a person hour is a unit of measure representing one person working for one hour. A construction foreman estimates it will take 2880 ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.