A plumbing contractor bid the rough-in work for a new three-story office building based an estimate of 850 hours of a journey-level plumber's time on the job. After the job was in progress, the contractor determined that the first floor required 342 hours and the second floor required 329 hours. How many labor hours are left in the estimate to complete the third floor?

+4
Answers (1)
  1. 2 December, 08:04
    0
    There is 179 hours left.

    -Hiadamcom
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A plumbing contractor bid the rough-in work for a new three-story office building based an estimate of 850 hours of a journey-level ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.