The design of a concrete mix requires 2,314 lb/yd3 of gravel having a moisture content of 3.5% and absorption of 4.2%, and 899 lb/yd3 of sand having a moisture content of 5.7% and absorption of 1.4%, and 244 lb/yd3 of free water. What is the weight of the mixing water per cubic yard that should be used at the job site?
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The design of a concrete mix requires 2,314 lb/yd3 of gravel having a moisture content of 3.5% and absorption of 4.2%, and 899 lb/yd3 of ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.