A construction company wants to hire carpenters for $220 a day and plumbers for $260 a day. The company wants to hire at least 18 workers. It wants to pay no more than $4500 each day.

Can the company hire 6 carpenters and 12 plumbers? Explain.

+5
Answers (1)
  1. 2 April, 05:17
    0
    Step-by-step explanation:

    Yes the company can hire 6 carpenters and 12 pumbers

    So first lets find out how much it costs to have 6 carpenter for $220 a day.

    $220 * 6 = $1320 this is how much it cost to pay 6 carpenters for one day.

    Now lets find how much it cost to 12 plumbers at $260 a day.

    $260 * 12 = $3120 this is how much it costs to pay 12 plumbers a day.

    The total amount you have to pay to the workers is:

    $3120 + $1320 = $4440

    Your budget was $4500 so the total costs for the workers is $4440 which means you can hire those workers and you would still have $60.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A construction company wants to hire carpenters for $220 a day and plumbers for $260 a day. The company wants to hire at least 18 workers. ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.