Ask Question
16 July, 04:32

A given project's expected duration along its critical path is 50 days, based on optimistic, most likely, and pessimistic duration estimates. What is the probability that the project will finish on or before 50 days?

+1
Answers (1)
  1. 16 July, 04:46
    0
    As critical path is the longest path during estimation, so 50 days is maximum time to complete this project. So probability to complete a project before 0n 50 days or before 50 days days is 1

    Pr=1
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “A given project's expected duration along its critical path is 50 days, based on optimistic, most likely, and pessimistic duration ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.
Search for Other Answers