It takes 14 electricians 18 days to wire a new housing subdivision. How many days would it take 24 electricians to do the same job?

+1
Answers (2)
  1. 5 August, 19:16
    0
    Answer = 21/2 days or 10 and 1/2 days

    It takes 14 electricians 18 days to wire a new housing subdivision.

    One electrician take more time to wire a new housing subdivision.

    So one electrician take 14 x 18 days to complete the job.

    Therefore 24 electricians take less time to complete the job.

    Number of days taken by 24 electricians to wire a new housing subdivision. = (14 x 18) / 24=21/2 days

    Therefor 24 electricians take (14 x 18) / 24=21/2 days
  2. 5 August, 21:51
    0
    10.5 days
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “It takes 14 electricians 18 days to wire a new housing subdivision. How many days would it take 24 electricians to do the same job? ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.