Problem 11-93 Waltner Corporation s management ... Waltner Corporation's management reports that its average delivery cycle time is 25 days, its average throughput time is 7.7 days, its manufacturing cycle efficiency (MCE) is 0.43, its average move time is 0.3 day, and its average queue time is 3.00 days. Required: a. What is the wait time

+5
Answers (1)
  1. 10 December, 01:21
    0
    Complete question is;

    Waltner Corporation's management reports that its average delivery cycle time is 25 days, its average throughput time is 7.7 days, its manufacturing cycle efficiency (MCE) is 0.43, its average move time is 0.3 day, and its average queue time is 3.00 days. Required: a. What is the wait time?

    b. What is the process time?

    c. What is the inspection time?

    Answer:

    A) Wait time = 17.3 days

    B) Process time = 3.311 days

    C) Inspection time = 0.789 days

    Step-by-step explanation:

    A) we are given;

    Delivery cycle time = 25 days

    throughput time = 7.7 days

    The formula for wait time is calculated from;

    Delivery time = wait time + throughput time

    So, wait time = Delivery time - throughput time

    Wait time = 25 - 7.7 = 17.3 days

    B) The process time is calculated from;

    MCE = Process time/throughput time

    So, process time = MCE x throughput time

    We are given MCE = 0.43, thus, and we already know throughput time. Thus;

    Process time = 0.43 x 7.7 = 3.311 days

    C) The inspection time is gotten from;

    throughput time = Process time + Inspection time + Move time + Queue time

    Making inspection time the subject;

    inspection time = throughput time - Process time - Move time - Queue time

    Move time = 0.3 days

    Queue time = 3 days.

    Thus;

    inspection time = 7.7 - 3.311 - 0.3 - 3.3 = 0.789 days
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Problem 11-93 Waltner Corporation s management ... Waltner Corporation's management reports that its average delivery cycle time is 25 ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.