shawna can pour a large concrete driveway in six hours. Dan can pour the same driveway in seven hours. Find how long it would take them if they worked together?

+2
Answers (1)
  1. 3 May, 05:03
    0
    work in rates per hour : -

    1/6 + 1/7 = 1/x

    Multiply through by the LCD, 42x:-

    7x + 6x = 42

    x = 42 / 13 = 3.23 hours answer

    or about 3 hours 14 minutes
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “shawna can pour a large concrete driveway in six hours. Dan can pour the same driveway in seven hours. Find how long it would take them if ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.