When building a house, the number of days required to build is inversely proportional to with the number of workers. One house was built in 11 days by 27 workers. How many days would it take to build a similar house with 3 workers?

+2
Answers (1)
  1. 14 December, 15:42
    0
    99 days

    Step-by-step explanation:

    With 1/9 the number of workers, it will take 1 / (1/9) = 9 times the number of days:

    9·11 days = 99 days
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “When building a house, the number of days required to build is inversely proportional to with the number of workers. One house was built in ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.