If the standard to produce a given amount of product is 2,000 units of direct materials at $12 and the actual direct materials used are 1,600 units at $13, the direct materials quantity variance is $5,200 favorable.

+5
Answers (1)
  1. 10 August, 04:51
    0
    The answer is FALSE

    Step-by-step explanation:

    Materials quantity variance = (SQ - AQ) * SP

    = (2,000 - 1,600) * 12

    $4800 Favourable
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “If the standard to produce a given amount of product is 2,000 units of direct materials at $12 and the actual direct materials used are ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.