10 people can paint a building in 5 days. If each person moves as quickly as others then how much of a building can 7 people paint in 5 days

+3
Answers (1)
  1. 2 September, 07:15
    0
    The entire job is 10*5 = 50

    7 people in 5 days will do 7 * 5. That is 35.

    So, it is 35/50 = 7/10 = 0.7 of the job or 70%.

    Does this make sense?
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “10 people can paint a building in 5 days. If each person moves as quickly as others then how much of a building can 7 people paint in 5 days ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.