How long will it take 5 workers to complete a task, given that 8 workers can compete the same task in 10 days?

+5
Answers (1)
  1. 11 August, 15:11
    0
    8 workers can complete a task in 10 days, meaning the man-hours needed to this task is 80 man-hours.

    Hence for 5 workers to complete the same task that require 80 man-hours, 80:5 = 16.

    So, it will take 16 days for 5 workers to complete this task.