Bonita has a standard of 2 hours of labor per unit, at $12 per hour. In producing 2600 units, Bonita used 5050 hours of labor at a total cost of $61610. Bonita's labor quantity variance is

+5
Answers (1)
  1. 26 May, 16:06
    0
    1800

    Step-by-step explanation:

    Labor quantity variance = Actual quantity * standard price - standard quantity * standard price

    Standard quantity=2*2600=5200

    Labor quantity variance

    5050*12-5200*12=1800
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Bonita has a standard of 2 hours of labor per unit, at $12 per hour. In producing 2600 units, Bonita used 5050 hours of labor at a total ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.