90 men can complete a work in 24 days working 8 hrs a day. how many men are required to complete the same work in 18 days working 15/2 hrs a day

+3
Answers (1)
  1. 31 December, 15:49
    0
    128 men

    Step-by-step explanation:

    90 * 28 * 8 = M * 18 * 15/2

    M = 128
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “90 men can complete a work in 24 days working 8 hrs a day. how many men are required to complete the same work in 18 days working 15/2 hrs ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.