Six people paint the fence and 15 hours how long would it take five workers to do the same job

+1
Answers (1)
  1. 30 March, 19:18
    0
    It will take 12.5 hrs for five workers to do the same job.

    steps:

    15 * 5 = 75

    75 : 6 = 12.5