a contractor estimates that he can paint a house in 5 days using 6 men. if he actually uses 5 men for the job, how many days will they take to paint the house?

+5
Answers (2)
  1. 3 August, 22:02
    0
    1 house = 6 men x 5 days = 30 man days

    Need 30 man days with only 5 men: 30x = 5 men → x = 6

    It will take 6 days for 5 men to complete the job.

    Answer: 6 days
  2. 3 August, 22:44
    0
    It will take 4 days to paint the house with 5 men
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “a contractor estimates that he can paint a house in 5 days using 6 men. if he actually uses 5 men for the job, how many days will they take ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.