An automobile maker has an order for 7,500 new cars to be delivered in one week. Each car must be fitted with a new hood ornament that requires 1 hour and 15 minutes to install. Assuming the factory operates on a standard workweek shift (8 hours per day for 5 days), how many workers must be assigned this job to meet the deadline?

... ?

+3
Answers (1)
  1. 30 September, 23:50
    0
    Time to fit 7500 cars = 7500 * 1.25 hoursnumber of hours available in week = 40 hoursnumber of workers needed = 7500 * 1.25 / 40 = 234.4number required = 235
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “An automobile maker has an order for 7,500 new cars to be delivered in one week. Each car must be fitted with a new hood ornament that ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.