If a new sidewalk will be 5 feet wide, 100 feet long and filled to a depth of 9 inches (0.75 foot) with concrete how many cubic yards of concrete are needed

+5
Answers (1)
  1. 6 January, 13:01
    0
    (5 ft) * (100 ft) * (0.75 ft) * ((1 yd) / (3 ft)) ³ ≈ 13 8/9 yd³

    About 13.89 cubic yards of concrete are needed.
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “If a new sidewalk will be 5 feet wide, 100 feet long and filled to a depth of 9 inches (0.75 foot) with concrete how many cubic yards of ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.