The total cost for a job is 1,766. the cost for material is 847.00. 3 employees are paid 8 dollars an hour for 22 hours of work. what is your profit

+2
Answers (1)
  1. 13 March, 23:45
    0
    Total cost = 1766

    Material cost=847

    3 employees are paid 8 dollars an hour for 22 hours so

    Labor cost=8*22=176

    Profit=total cost - (material cost+labor cost)

    Profit=1,766 - (847+176) = 743
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “The total cost for a job is 1,766. the cost for material is 847.00. 3 employees are paid 8 dollars an hour for 22 hours of work. what is ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.