It takes an older employee 13 hours to shovel the snow from a sidewalk, but a younger employee can shovel the same sidewalk in 10 hours. how long will it take them to clear the walk if they work together?

+1
Answers (1)
  1. 22 January, 22:19
    0
    Work in rates per hour. These rates can then be added to form an equation

    1/13 + 1/10 = 1/x where x is the time for both working together

    multiply thru by 130x:-

    10 x + 13 x = 130

    x = 130/23 = 5.65 hours or about 6 hours 39 minutes
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “It takes an older employee 13 hours to shovel the snow from a sidewalk, but a younger employee can shovel the same sidewalk in 10 hours. ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.