Suppose that the time it takes to do a job is inversely proportional to the number of workers. that is, the more workers on the job the less time required to complete the job. if it takes 2 workers 8 days to finish a job, how long will it take 8 workers?

+1
Answers (1)
  1. 2 January, 07:59
    0
    I think it would be 2 days. you would get it done 4 times faster, so 8/4 is 2
Know the Answer?
Not Sure About the Answer?
Get an answer to your question ✅ “Suppose that the time it takes to do a job is inversely proportional to the number of workers. that is, the more workers on the job the ...” in 📙 Mathematics if there is no answer or all answers are wrong, use a search bar and try to find the answer among similar questions.